Tuesday, November 27, 2012

Artificial Turf Installation - VIVATURF


Before the construction of foundation in play, flatness, gradient and surface perceptions were detected, proposed trimming measures and requirements. After all things meet the requirements, we can construction approach.

Put line ( measurement ), identify the site to the center point and the two semicircle circle, and the three positioning points on the feet pull, set out the midline and edge intersection, and then to the Pythagorean theorem set out on the point, line and accurate location, set the function point, line position; and with the ink or paint line popup.

Turf moved venues along the lateral edge direction to spread to the other end, and sequentially from one end of the longitudinal edges of propulsion, spread out, as far as possible so that the white woven on the turf scribe in function line position, to reduce the number of cutting;

Cut woven turf outer edge of the white grass lines and not placed on the function line location, placed side stand, the white crossed another woven by hand must be cut into a 12CM wide white draw lines;

Lap seams of green turf 2-3 cm, cut grass push knife from the central incision lap lap compact as possible, so that both sides of the turf, and then to the cutter trim;

Swing, the connecting band 20 or 30 cm wide along the artificial turf seams into the sod turf try to make seams located in connection with the center (if wet by rain, half a day to dry the required drying), and then purpose adhesive water evenly with a rubber scraper scraping connected to the belt, then on both sides of the turf Flatten adhesive in connection bring, and beat with a rubber hammer, so that the combination of partial bonding closely. If straightened and put together at the gap here cut 2-5 cm intervals, stretching to the interface, in order to ensure a beautiful appearance;

Turf basic splicing After again PULL fixed function line, the exact location of the point to the cutter cut out of the cut grass strips, the connecting band into Scratch glue originally prepared white The grass line back in, cementation, repeatedly beat with a rubber hammer, in order to be part of the bond closely connected.

Turf paving mosaic after the turf on the part of the Folding knife opening, straightened docking, the removal of the overlapping part, and then cemented;

Turf all bonding is completed, start with a brush grass machine to sort out: first pass audience lodging grass line comb Brush grass machine upright.

According to the 4M*4M specifications to the discharge point, according to different high grass per square meter kilogram of quartz sand injection uniform spreading into the specified area, with brushing machine will Ishim Elisa spread evenly and grass lines and vertical carding, combing once.

Filling is completed, and then brush grass machine the grass fiber aspect combing each time.
After the completion of the work, in accordance with the VIVAITURF artificial turf surface quality requirements for detection and clearance, to unqualified for rectification;